Supplementary estimates of appropriations

Vote Prime Minister and Cabinet - Supplementary Estimates 2018/19

Vote Prime Minister and Cabinet#

APPROPRIATION MINISTER(S): Minister of Civil Defence (M11), Prime Minister (M52), Minister for Greater Christchurch Regeneration (M85), Minister Responsible for the Earthquake Commission (M86)

APPROPRIATION ADMINISTRATOR: Department of the Prime Minister and Cabinet

RESPONSIBLE MINISTER FOR DEPARTMENT OF THE PRIME MINISTER AND CABINET: Prime Minister

Details of Appropriations and Capital Injections#

Annual Appropriations and Forecast Permanent Appropriations#

  2018/19
Titles and Scopes of Appropriations by Appropriation Type Estimates
Budget
$000
Supplementary
Estimates
Budget
$000
Total
Budget
$000

Departmental Output Expenses

     

Canterbury Earthquake Recovery (M85)

This appropriation is limited to provision of services supporting the regeneration of greater Christchurch.
10,784 785 11,569

Support for Inquiry into EQC (M86)

This appropriation is limited to supporting the Inquiry into EQC.
1,782 306 2,088

Total Departmental Output Expenses

12,566 1,091 13,657

Departmental Capital Expenditure

     

Department of the Prime Minister and Cabinet - Capital Expenditure PLA (M52)

This appropriation is limited to the purchase or development of assets by and for the use of the Department of the Prime Minister and Cabinet, as authorised by section 24(1) of the Public Finance Act 1989.
400 568 968

Total Departmental Capital Expenditure

400 568 968

Non-Departmental Other Expenses

     

Civil Defence Emergency Management Training (M11)

This appropriation is limited to provision of training to learners/volunteers in the Civil Defence Emergency Management Sector.
- 1,000 1,000

Contributions to Local Authorities Following an Emergency Event (M11)

This appropriation is limited to contributions to local authorities (other than contributions authorised by section 115A of the Civil Defence Emergency Management Act 2002) following an emergency event, as prescribed in the current Guide to the National Civil Defence Emergency Management Plan.
1,900 - 1,900

Emergency Management Preparedness Grants (M11)

This appropriation is limited to projects endorsed by CDEM Groups and managed or supported by the Ministry of Civil Defence & Emergency Management.
889 159 1,048

Ex gratia payment to the University of Auckland (M52)

This appropriation is limited to ex gratia payments to the University of Auckland to enable continued support of Professor Sir Peter Gluckman's own specialised research programme during his membership of the Science Advisory Committee.
120 (120) -

Fair Value Write-down of Suspensory Loan for Christ Church Cathedral Reinstatement (M85)

This appropriation is limited to fair value write-down of the suspensory loan for the reinstatement of Christ Church Cathedral, in accordance with generally accepted accounting practice.
- 15,000 15,000

Governor-General's Programme PLA (M52)

This appropriation is limited to expenses incurred on the Governor-General's Programme, as authorised by section 13 of the Governor-General Act 2010.
1,239 261 1,500

Governor-General's Salary and Allowance PLA (M52)

This appropriation is limited to expenses incurred on the salary, allowance and other payments to the Governor-General, as authorised by section 12 of the Governor-General Act 2010.
500 - 500

Governor-General's travel outside New Zealand PLA (M52)

This appropriation is limited to expenses incurred on the Governor-General's travel outside New Zealand, as authorised by section 14 of the Governor-General Act 2010.
407 - 407

Inquiry into EQC (M86)

This appropriation is limited to the payment of fees and expenses for the Inquiry into EQC.
648 (468) 180

Local Authority Emergency Expenses PLA (M11)

This appropriation is limited to reimbursing a local authority for, or meeting, expenses incurred by a local authority in connection with an emergency as authorised by section 115A of the Civil Defence Emergency Management Act 2002.
5,000 - 5,000

Prime Minister's Chief Science Advisor Research Programme (M52)

This appropriation is limited to supporting the Prime Minister's Chief Science Advisor's specialised research programme during their membership of the Science Advisory Committee.
- 120 120

Rehabilitation of Kaikoura Harbour (M11)

This appropriation is limited to a contribution to the Kaikoura District Council acting on behalf of Environment Canterbury for work necessary to restore the functionality of Kaikoura Harbour.
300 - 300

Remuneration of Commissioners of Intelligence Warrants PLA (M52)

This appropriation is limited to the salaries and allowances of Commissioners of Intelligence Warrants as authorised by clause 3(1) of Schedule 3 of the Intelligence and Security Act 2017.
174 - 174

Restoration of Kaikoura District Three Waters Network (M11)

This appropriation is limited to a contribution to Kaikoura District Council to support additional resilience, capacity, improved materials, or other alternatives to the original infrastructure as part of restoration of essential infrastructure systems.
- 2,400 2,400

Total Non-Departmental Other Expenses

11,177 18,352 29,529

Non-Departmental Capital Expenditure

     

Suspensory Loan for Christ Church Cathedral Reinstatement (M85)

This appropriation is limited to provision of a suspensory loan for the reinstatement of Christ Church Cathedral.
- 15,000 15,000

Total Non-Departmental Capital Expenditure

- 15,000 15,000

Multi-Category Expenses and Capital Expenditure

     

Emergency Management MCA (M11)

The single overarching purpose of this appropriation is to support communities to be resilient by enhancing their capacity and capability to manage civil defence emergencies.
15,530 4,518 20,048

Departmental Output Expenses

     

Community Awareness and Readiness

This category is limited to the development and delivery of long-term national programmes to raise individual and community awareness and preparedness.
1,938 107 2,045

Emergency Sector and Support and Development

This category is limited to developing and implementing operational policies and projects, advice, assistance and information to the civil defence and emergency management sector.
5,644 1,800 7,444

Management of Emergencies

This category is limited to management of national emergency readiness, response and recovery, including support to local civil defence emergency management organisations, maintaining the National Crisis Management Centre in a state of readiness, national training and exercises, coordination and management of central government's response and recovery activities and administration of related expenses.
7,005 2,161 9,166

Policy Advice - Emergency Management

This category is limited to the provision of advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by Ministers on government policy matters relating to civil defence emergency matters.
943 450 1,393

Government House Buildings and Assets MCA (M52)

The overarching purpose of this appropriation is maintaining the Government House buildings and related assets in Wellington and Auckland to the standards necessary to fulfil their constitutional, ceremonial and community roles.
3,362 (135) 3,227

Non-Departmental Other Expenses

     

Depreciation of Crown Assets

This category is limited to depreciation expenses on the Government House buildings and related assets.
1,962 (750) 1,212

Government House - Maintenance

This category is limited to the ongoing maintenance of the Government House buildings and related assets, and the grounds on which they are located.
600 65 665

Non-Departmental Capital Expenditure

     

Government House - Capital Investment

This category is limited to investment necessary to preserve the functionality and value of the Government House buildings and related assets.
800 550 1,350

Policy Advice and Support Services MCA (M52)

The overarching purpose of this appropriation is to provide policy advice to support decision-making by the Prime Minister and the Cabinet and provide support services to the Prime Minister, Cabinet and its committees, the Executive Council, and the Governor General.
28,586 3,705 32,291

Departmental Output Expenses

     

National Security Priorities and Intelligence Coordination

This category is limited to leadership and coordination around national security matters, leading collaboration within the New Zealand intelligence community and providing intelligence assessments to support national security priorities.
11,417 1,051 12,468

Policy Advice - Child Poverty Reduction

This category is limited to advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by Ministers on government policy matters relating to child poverty reduction.
1,873 950 2,823

Policy Advice - Prime Minister and Cabinet

This category is limited to the provision of advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by the Prime Minister and the Cabinet.
4,542 1,018 5,560

Science Advisory Committee

This category is limited to the purchase of high-quality scientific advice to the Prime Minister.
675 50 725

Support Services to the Governor-General and Maintenance of the Official Residences

This category is limited to financial, administrative, communications and advisory services for the Governor-General; and services to maintain the Governor-General's residences.
4,139 425 4,564

Support, Secretariat and Coordination Services

This category is limited to the provision of services to Ministers to enable them to discharge their portfolio (other than policy decision-making) responsibilities including support for the coordination of the Government's legislation programme; secretariat services to the Executive Council, Cabinet and its committees; and administration of the New Zealand Honours system.
5,940 211 6,151

Tsunami Monitoring and Detection Network MCA (M11)

The single overarching purpose of this appropriation is to provide comprehensive monitoring, early detection and subsequent early warning of tsunami threats to New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).
- 5,752 5,752

Departmental Output Expenses

     

Management of Tsunami Monitoring and Detection Network

This category is limited to the on-going management and maintenance of a tsunami monitoring and detection network for New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).
- 204 204

Non-Departmental Capital Expenditure

     

Tsunami Monitoring and Detection Network - Capital Expenditure

This category is limited to capital expenditure necessary to acquire and preserve the functionality of a tsunami monitoring and detection network for New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).
- 5,548 5,548

Total Multi-Category Expenses and Capital Expenditure

47,478 13,840 61,318

Total Annual Appropriations and Forecast Permanent Appropriations

71,621 48,851 120,472

Multi-Year Appropriations#

Type, Title, Scope and Period of Appropriations Appropriations, Adjustments and Use $000

Non-Departmental Output Expenses

   

Regenerate Christchurch (M85)

This appropriation is limited to establishment costs and the development of strategies and planning activities, with communities, stakeholders and decision-makers, for the regeneration of areas in Christchurch.

Commences: 01 July 2016

Expires: 30 June 2021
Original Appropriation 20,000
Adjustments to 2017/18 1,073
Adjustments for 2018/19 -
Adjusted Appropriation 21,073
Actual to 2017/18 Year End 8,000
Estimated Actual for 2018/19 5,073
Estimate for 2019/20 4,000
Estimated Appropriation Remaining 4,000

Total Annual Appropriations and Forecast Permanent Appropriations and Multi-Year Appropriations#

  2018/19
  Estimates
Budget
$000
Supplementary
Estimates
Budget
$000
Total
Budget
$000
Total Annual Appropriations and Forecast Permanent Appropriations 71,621 48,851 120,472
Total Forecast MYA Non-Departmental Output Expenses 5,073 - 5,073

Total Annual Appropriations and Forecast Permanent Appropriations and Multi-Year Appropriations

76,694 48,851 125,545

Capital Injection Authorisations#

  2018/19
  Estimates Budget
$000
Supplementary
Estimates Budget
$000
Total Budget
$000
Department of the Prime Minister and Cabinet - Capital Injection (M52) 300 368 668

Supporting Information#

Part 1 - Vote as a Whole#

Summary of Financial Activity
  2018/19
    Supplementary Estimates  
  Estimates
$000
Departmental
Transactions
$000
Non-Departmental
Transactions
$000
Total
Transactions
$000
Total
$000

Appropriations

         
Output Expenses 17,639 1,091 - 1,091 18,730
Benefits or Related Expenses - N/A - - -
Borrowing Expenses - - - - -
Other Expenses 11,177 - 18,352 18,352 29,529
Capital Expenditure 400 568 15,000 15,568 15,968
Intelligence and Security Department Expenses and Capital Expenditure - - N/A - -
Multi-Category Expenses and Capital Expenditure (MCA)          
Output Expenses 44,116 8,427 - 8,427 52,543
Other Expenses 2,562 - (685) (685) 1,877
Capital Expenditure 800 N/A 6,098 6,098 6,898

Total Appropriations

76,694 10,086 38,765 48,851 125,545

Crown Revenue and Capital Receipts

         
Tax Revenue - N/A - - -
Non-Tax Revenue 150 N/A 2,200 2,200 2,350
Capital Receipts - N/A - - -

Total Crown Revenue and Capital Receipts

150 N/A 2,200 2,200 2,350

Part 2 - Details of Departmental Appropriations#

2.1 - Departmental Output Expenses#

Canterbury Earthquake Recovery (M85)
Scope of Appropriation
This appropriation is limited to provision of services supporting the regeneration of greater Christchurch.
Expenses and Revenue
  2018/19
  Estimates
$000
Supplementary
Estimates
$000
Total
$000
Total Appropriation 10,784 785 11,569
Revenue from the Crown 10,784 600 11,384
Revenue from Others - 185 185
Reasons for Change in Appropriation

This appropriation increased by $785,000 to $11.569 million for 2018/19 due to:

  • $800,000 for a transfer from 2017/18 to support the Canterbury Earthquake Recovery
  • $800,000 for a transfer from 2017/18 for the costs of litigation that was not concluded in 2017/18, and
  • $185,000 revenue for the sub-lease of Christchurch property.

The increase was partially offset by:

  • $1 million expense transfer from 2018/19 to 2019/20 to reflect uncertainties in activities associated with the Canterbury Earthquake Recovery.
Support for Inquiry into EQC (M86)
Scope of Appropriation
This appropriation is limited to supporting the Inquiry into EQC.
Reasons for Change in Appropriation

This appropriation increased by $306,000 to $2.088 million for 2018/19 due to:

  • $614,000 for a fiscally neutral transfer from the non-departmental other expenses appropriation: Inquiry into EQC, as a result of a reduction in the number of Inquiry board members and the consequent need for additional departmental staff, and
  • $592,000 for a transfer from 2017/18 to reflect the late start to the Inquiry.

The increase was partly offset by:

  • $900,000 expense transfer from 2018/19 due to the Inquiry now being scheduled to finish later than originally planned.

2.3 - Departmental Capital Expenditure and Capital Injections#

Department of the Prime Minister and Cabinet - Capital Expenditure PLA (M52)
Scope of Appropriation
This appropriation is limited to the purchase or development of assets by and for the use of the Department of the Prime Minister and Cabinet, as authorised by section 24(1) of the Public Finance Act 1989.
Capital Expenditure
  2018/19
  Estimates
$000
Supplementary
Estimates
$000
Total
$000
Forests/Agricultural - - -
Land - - -
Property, Plant and Equipment 350 568 918
Intangibles - - -
Other 50 - 50

Total Appropriation

400 568 968
Reasons for Change in Appropriation

This appropriation increased by $568,000 to $968,000 for 2018/19 due to:

  • $368,000 for the establishment of civil defence Fly-In Teams, and
  • $200,000 for the expected cost of replacement of the Department's fixed assets according to the approved capital plan.
Capital Injections and Movements in Departmental Net Assets
Department of the Prime Minister and Cabinet
Details of Net Asset Schedule 2018/19
Main Estimates Projections
$000
2018/19
Supplementary Estimates Projections
$000
Explanation of Projected Movements in 2018/19
Opening Balance 8,297 8,297 Supplementary Estimates opening balance reflects the audited results as at 30 June 2018.
Capital Injections 300 668 Capital injection for the direction, coordination and provision of intelligence assessments to support national intelligence priorities and provide for the establishment of Fly-In Teams.
Capital Withdrawals - -  
Surplus to be Retained (Deficit Incurred) - -  
Other Movements - -  

Closing Balance

8,597 8,965  

Part 3 - Details of Non-Departmental Appropriations#

3.4 - Non-Departmental Other Expenses#

Civil Defence Emergency Management Training (M11)
Scope of Appropriation
This appropriation is limited to provision of training to learners/volunteers in the Civil Defence Emergency Management Sector.
Expenses
  2018/19
  Estimates
$000
Supplementary Estimates
$000
Total
$000
Total Appropriation - 1,000 1,000
What is Intended to be Achieved with this Appropriation

This appropriation is intended to achieve the purchasing of required skills-based training programmes for Civil Defence Emergency Management (CDEM) learners and volunteers.

How Performance will be Assessed and End of Year Reporting Requirements
  2018/19
Performance Measures Estimates
Standard
Supplementary
Estimates
Standard
Total
Standard

Satisfaction is at least 6 in relation to the measure below (see Note 1):

     
  • Civil defence emergency management training courses meet participants' expectations (see Note 2)
New Measure 6 6

Note 1 - Course participants to complete satisfaction survey.

Note 2 - Satisfaction is measured on a 10-point scale, where 1 means fell well short of expectations and 10 means far exceeded expectations.

End of Year Performance Reporting

Performance information for this appropriation will be reported by the Minister of Civil Defence in a report appended to the Department of the Prime Minister and Cabinet's 2018/19 Annual Report.

Reasons for Change in Appropriation

The increase in this appropriation by $1 million is due to it being a new appropriation in 2018/19.

Emergency Management Preparedness Grants (M11)
Scope of Appropriation
This appropriation is limited to projects endorsed by CDEM Groups and managed or supported by the Ministry of Civil Defence & Emergency Management.
Reasons for Change in Appropriation

This appropriation increased by $159,000 to $1.048 million for 2018/19 due to a transfer from 2017/18 reflecting uncertainty around the timing of expenditure.

Ex gratia payment to the University of Auckland (M52)
Scope of Appropriation
This appropriation is limited to ex gratia payments to the University of Auckland to enable continued support of Professor Sir Peter Gluckman's own specialised research programme during his membership of the Science Advisory Committee.
Reasons for Change in Appropriation

The appropriation was disestablished in early 2018/19 and replaced by a new non-departmental other expense appropriation: Prime Minister's Chief Science Advisor Research Programme.

Fair Value Write-down of Suspensory Loan for Christ Church Cathedral Reinstatement (M85)
Scope of Appropriation
This appropriation is limited to fair value write-down of the suspensory loan for the reinstatement of Christ Church Cathedral, in accordance with generally accepted accounting practice.
Expenses
  2018/19
  Estimates
$000
Supplementary Estimates
$000
Total
$000
Total Appropriation - 15,000 15,000
What is Intended to be Achieved with this Appropriation

This appropriation is intended to achieve the write-down of the suspensory loan for Christ Church Cathedral reinstatement.

End of Year Performance Reporting

An exemption was granted under section 15D(2)(b)(ii) of the Public Finance Act 1989 on the basis that any expenses associated with fair value write-down are non-cash and for accounting purposes only, and so any performance information would not likely be informative.

Reasons for Change in Appropriation

This appropriation increased by $15 million to $15 million for 2018/19 due to an expense transfer from 2017/18 to support the costs of the write-down of the suspensory loan for the Christ Church Cathedral Reinstatement.

Governor-General's Programme PLA (M52)
Scope of Appropriation
This appropriation is limited to expenses incurred on the Governor-General's Programme, as authorised by section 13 of the Governor-General Act 2010.
Reasons for Change in Appropriation

This appropriation increased by $261,000 to $1.500 million for 2018/19 due to a forecast increase in costs for the approved programme of activities for the Governor-General.

Inquiry into EQC (M86)
Scope of Appropriation
This appropriation is limited to the payment of fees and expenses for the Inquiry into EQC.
Reasons for Change in Appropriation

This appropriation decreased by $468,000 to $180,000 for 2018/19 due to:

  • $614,000 for a fiscally neutral transfer from the departmental output expense appropriation: Support for Inquiry into EQC, as a result of a reduction in the number of Inquiry board members and the consequent need for additional departmental staff, and
  • $70,000 for an expense transfer to 2019/20 due to the Inquiry being scheduled to finish later than originally planned.

The decrease was partly offset by:

  • $216,000 for a transfer from 2017/18 to reflect the late start to the Inquiry.
Prime Minister's Chief Science Advisor Research Programme (M52)
Scope of Appropriation
This appropriation is limited to supporting the Prime Minister's Chief Science Advisor's specialised research programme during their membership of the Science Advisory Committee.
Expenses
  2018/19
  Estimates
$000
Supplementary Estimates
$000
Total
$000
Total Appropriation - 120 120
What is Intended to be Achieved with this Appropriation

This appropriation is intended to achieve the provision of high-quality scientific advice to the Prime Minister.

How Performance will be Assessed and End of Year Reporting Requirements

An exemption was granted under section 15D(2)(b)(iii) of the Public Finance Act 1989 on the basis that the amount (or annual average equivalent) of the appropriation is less than $5 million for expenses.

Reasons for Change in Appropriation

This is a new appropriation in 2018/19 to replace the previous non-departmental other expense appropriation: Ex Gratia Payment to the University of Auckland.

Restoration of Kaikoura District Three Waters Network (M11)
Scope of Appropriation
This appropriation is limited to a contribution to Kaikoura District Council to support additional resilience, capacity, improved materials, or other alternatives to the original infrastructure as part of restoration of essential infrastructure systems.
Expenses
  2018/19
  Estimates
$000
Supplementary Estimates
$000
Total
$000
Total Appropriation - 2,400 2,400
What is Intended to be Achieved with this Appropriation

This appropriation is intended to achieve some additional resilience, capacity or other improvements where appropriate to the Kaikoura District three waters network.

How Performance will be Assessed and End of Year Reporting Requirements
  2018/19
Performance Measures Estimates
Standard
Supplementary
Estimates
Standard
Total
Standard

Additional work scope over and above a "like for like" repair or replacement must be recommended by the Kaikoura Rebuild Steering Group and must meet the requirements of the Memorandum of Understanding: drawdown of restoration of three waters appropriation (see Note 1)

New Measure Achieved Achieved

Note 1 - "Achieved' would be supported by the following - a copy of the Memorandum of Understanding, a copy of the steering group minute, a copy of the business case for the project/s or betterment work scope.

End of Year Performance Reporting

Performance information for this appropriation will be reported by the Minister of Civil Defence in a report appended to the Department of the Prime Minister and Cabinet's 2018/19 Annual Report.

Reasons for Change in Appropriation

This appropriation increased by $2.400 million to $2.400 million for 2018/19 due to a funding transfer from 2017/18 to support the restoration of the Kaikoura District Council's essential infrastructure assets.

3.5 - Non-Departmental Capital Expenditure#

Suspensory Loan for Christ Church Cathedral Reinstatement (M85)
Scope of Appropriation
This appropriation is limited to provision of a suspensory loan for the reinstatement of Christ Church Cathedral.
Capital Expenditure
  2018/19
  Estimates
$000
Supplementary Estimates
$000
Total
$000
Total Appropriation - 15,000 15,000
What is Intended to be Achieved with this Appropriation

This appropriation is intended to achieve the implementation of the Crown's offer to support the reinstatement of Christ Church Cathedral.

How Performance will be Assessed and End of Year Reporting Requirements
  2018/19
Performance Measures Estimates
Standard
Supplementary
Estimates
Standard
Total
Standard

Terms and criteria for advancing the $15 million suspensory loan to support the Christ Church Cathedral reinstatement have been met and the suspensory loan has been advanced

New Measure Achieved Achieved
End of Year Performance Reporting

Performance information for this appropriation will be reported by the Minister for Greater Christchurch Regeneration in a report appended to the Department of the Prime Minister and Cabinet's 2018/19 Annual Report.

Reasons for Change in Appropriation

This appropriation increased by $15 million to $15 million for 2018/19 due to an expense transfer from 2017/18 to support the costs of the suspensory loan for the Christ Church Cathedral Reinstatement.

Part 4 - Details of Multi-Category Expenses and Capital Expenditure#

Multi-Category Expenses and Capital Expenditure#

Emergency Management (M11)
Overarching Purpose Statement
The single overarching purpose of this appropriation is to support communities to be resilient by enhancing their capacity and capability to manage civil defence emergencies.
Scope of Appropriation
Departmental Output Expenses
Community Awareness and Readiness
This category is limited to the development and delivery of long-term national programmes to raise individual and community awareness and preparedness.
Emergency Sector and Support and Development
This category is limited to developing and implementing operational policies and projects, advice, assistance and information to the civil defence and emergency management sector.
Management of Emergencies
This category is limited to management of national emergency readiness, response and recovery, including support to local civil defence emergency management organisations, maintaining the National Crisis Management Centre in a state of readiness, national training and exercises, coordination and management of central government's response and recovery activities and administration of related expenses.
Policy Advice - Emergency Management
This category is limited to the provision of advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by Ministers on government policy matters relating to civil defence emergency matters.
Expenses, Revenue and Capital Expenditure
  2018/19
  Estimates
$000
Supplementary Estimates
$000
Total
$000

Total Appropriation

15,530 4,518 20,048

Departmental Output Expenses

     
Community Awareness and Readiness 1,938 107 2,045
Emergency Sector and Support and Development 5,644 1,800 7,444
Management of Emergencies 7,005 2,161 9,166
Policy Advice - Emergency Management 943 450 1,393

Funding for Departmental Output Expenses

     

Revenue from the Crown

15,300 3,011 18,311
Community Awareness and Readiness 1,915 100 2,015
Emergency Sector and Support and Development 5,523 300 5,823
Management of Emergencies 6,919 2,161 9,080
Policy Advice - Emergency Management 943 450 1,393

Revenue from Others

230 1,507 1,737
Community Awareness and Readiness 23 7 30
Emergency Sector and Support and Development 121 1,500 1,621
Management of Emergencies 86 - 86
Reasons for Change in Appropriation

This appropriation increased by $4.518 million to $20.048 million for 2018/19 due to:

  • $1.507 million for revenue received from the Ministry of Foreign Affairs and Trade to support emergency resilience programmes
  • $1.220 million for transfers from 2017/18 due to delays in projects and programmes, and uncertainties around the timing of expenditure
  • $941,000 for the establishment of Fly-In Teams to support responses to emergencies in New Zealand
  • $400,000 for the development of a business case for a Common Operating Picture
  • $250,000 for developing a stage 1 business case for a new national emergency management facility, and
  • $200,000 for work on legislative change necessary to support the proposals in response to the review of New Zealand's emergency response system.
Government House Buildings and Assets (M52)
Overarching Purpose Statement
The overarching purpose of this appropriation is maintaining the Government House buildings and related assets in Wellington and Auckland to the standards necessary to fulfil their constitutional, ceremonial and community roles.
Scope of Appropriation
Non-Departmental Other Expenses
Depreciation of Crown Assets
This category is limited to depreciation expenses on the Government House buildings and related assets.
Government House - Maintenance
This category is limited to the ongoing maintenance of the Government House buildings and related assets, and the grounds on which they are located.
Loss on Disposal of Crown Assets
This category is limited to loss on disposal of Government House precinct buildings and related assets.
Non-Departmental Capital Expenditure
Government House - Capital Investment
This category is limited to investment necessary to preserve the functionality and value of the Government House buildings and related assets.
Expenses, Revenue and Capital Expenditure
  2018/19
  Estimates
$000
Supplementary Estimates
$000
Total
$000

Total Appropriation

3,362 (135) 3,227

Non-Departmental Other Expenses

     
Depreciation of Crown Assets 1,962 (750) 1,212
Government House - Maintenance 600 65 665

Non-Departmental Capital Expenditure

     
Government House - Capital Investment 800 550 1,350
Reasons for Change in Appropriation

This appropriation decreased by $135,000 to $3.227 million for 2018/19 due to:

  • $535,000 for fiscally neutral transfers to other appropriations to align the resource requirements with demand and activities.

The decrease was partially offset by:

  • $400,000 for transfers from 2017/18 due to delays in projects and programmes, and uncertainties around the timing of expenditure.

 

Policy Advice and Support Services (M52)
Overarching Purpose Statement
The overarching purpose of this appropriation is to provide policy advice to support decision-making by the Prime Minister and the Cabinet and provide support services to the Prime Minister, Cabinet and its committees, the Executive Council, and the Governor General.
Scope of Appropriation
Departmental Output Expenses
National Security Priorities and Intelligence Coordination
This category is limited to leadership and coordination around national security matters, leading collaboration within the New Zealand intelligence community and providing intelligence assessments to support national security priorities.
Policy Advice - Child Poverty Reduction
This category is limited to advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by Ministers on government policy matters relating to child poverty reduction.
Policy Advice - Prime Minister and Cabinet
This category is limited to the provision of advice (including second opinion advice and contributions to policy advice led by other agencies) to support decision-making by the Prime Minister and the Cabinet.
Science Advisory Committee
This category is limited to the purchase of high-quality scientific advice to the Prime Minister.
Support Services to the Governor-General and Maintenance of the Official Residences
This category is limited to financial, administrative, communications and advisory services for the Governor-General; and services to maintain the Governor-General's residences.
Support, Secretariat and Coordination Services
This category is limited to the provision of services to Ministers to enable them to discharge their portfolio (other than policy decision-making) responsibilities including support for the coordination of the Government's legislation programme; secretariat services to the Executive Council, Cabinet and its committees; and administration of the New Zealand Honours system.
Expenses, Revenue and Capital Expenditure
  2018/19
  Estimates
$000
Supplementary Estimates
$000
Total
$000

Total Appropriation

28,586 3,705 32,291

Departmental Output Expenses

     
National Security Priorities and Intelligence Coordination 11,417 1,051 12,468
Policy Advice - Child Poverty Reduction 1,873 950 2,823
Policy Advice - Prime Minister and Cabinet 4,542 1,018 5,560
Science Advisory Committee 675 50 725
Support Services to the Governor-General and Maintenance of the Official Residences 4,139 425 4,564
Support, Secretariat and Coordination Services 5,940 211 6,151

Funding for Departmental Output Expenses

     

Revenue from the Crown

28,556 1,537 30,093
National Security Priorities and Intelligence Coordination 11,417 544 11,961
Policy Advice - Child Poverty Reduction 1,873 950 2,823
Policy Advice - Prime Minister and Cabinet 4,542 (532) 4,010
Science Advisory Committee 675 - 675
Support Services to the Governor-General and Maintenance of the Official Residences 4,109 425 4,534
Support, Secretariat and Coordination Services 5,940 150 6,090

Revenue from Others

30 2,168 2,198
National Security Priorities and Intelligence Coordination - 507 507
Policy Advice - Prime Minister and Cabinet - 1,550 1,550
Science Advisory Committee - 50 50
Support Services to the Governor-General and Maintenance of the Official Residences 30 - 30
Support, Secretariat and Coordination Services - 61 61
Reasons for Change in Appropriation

This appropriation increased by $3.705 million to $32.291 million for 2018/19 due to:

  • $2.168 million for revenue received from other agencies to support the Policy Project, the Science Committee and the continuation of development programmes for the national security workforce, as well as recoveries of staff secondment costs and receipts from sales of honours and awards insignia
  • $1.025 million for transfers from 2017/18 due to delays in projects and programmes, and uncertainties around the timing of expenditure, and
  • $594,000 for fiscally neutral transfers from other appropriations to align resource requirements with demand and activities.

The increase was partly offset by:

  • $82,000 transferred to Vote Internal Affairs as a contribution to infrastructure improvements.
Tsunami Monitoring and Detection Network (M11)
Overarching Purpose Statement
The single overarching purpose of this appropriation is to provide comprehensive monitoring, early detection and subsequent early warning of tsunami threats to New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).
Scope of Appropriation
Departmental Output Expenses
Management of Tsunami Monitoring and Detection Network
This category is limited to the on-going management and maintenance of a tsunami monitoring and detection network for New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).
Non-Departmental Capital Expenditure
Tsunami Monitoring and Detection Network - Capital Expenditure
This category is limited to capital expenditure necessary to acquire and preserve the functionality of a tsunami monitoring and detection network for New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).
Expenses, Revenue and Capital Expenditure
  2018/19
  Estimates
$000
Supplementary Estimates
$000
Total
$000

Total Appropriation

- 5,752 5,752

Departmental Output Expenses

     
Management of Tsunami Monitoring and Detection Network - 204 204

Non-Departmental Capital Expenditure

     
Tsunami Monitoring and Detection Network - Capital Expenditure - 5,548 5,548

Funding for Departmental Output Expenses

     

Revenue from the Crown

- 204 204
Management of Tsunami Monitoring and Detection Network - 204 204
What is Intended to be Achieved with this Appropriation

This appropriation is intended to achieve comprehensive monitoring, early detection and subsequent early warning of tsunami threats to New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).

How Performance will be Assessed for this Appropriation
  2018/19
Assessment of Performance Estimates
Standard
Supplementary Estimates
Standard
Total
Standard

The Tsunami Monitoring and Detection Network programme is managed within agreed timeframes

New measure Achieved Achieved
What is Intended to be Achieved with each Category and How Performance will be Assessed
  2018/19
Assessment of Performance Estimates
Standard
Supplementary Estimates
Standard
Total
Standard

Departmental Output Expenses

     

Management of Tsunami Monitoring and Detection Network

     

This category is limited to the on-going management and maintenance of a tsunami monitoring and detection network for New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).

     

The Tsunami Monitoring and Detection Network programme is delivered to schedule

New measure Achieved Achieved

Non-Departmental Capital Expenditure

     

Tsunami Monitoring and Detection Network - Capital Expenditure

     

This category is limited to capital expenditure necessary to acquire and preserve the functionality of a tsunami monitoring and detection network for New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).

     

DART Buoys contract negotiated and order placed

New measure Achieved Achieved
End of Year Performance Reporting

Performance information for this appropriation will be reported by the Department of the Prime Minister and Cabinet in the 2018/19 Annual Report.

Reasons for Change in Appropriation

This appropriation increased by $5.752 million to $5.752 million for 2018/19 due to a new policy decision to establish a comprehensive monitoring, early detection and subsequent early warning of tsunami threats to New Zealand and the Pacific Realm countries (Niue, Tokelau and the Cook Islands).